Changing the Katrina Cottage

October
13
2016

Little Choptank Nov.5 to 7, 2011 078

Lots going on around here in real-time.  We are packing up the Crab Shack, the kitchen and bathroom and mudroom that is, because the builders are starting in here on Monday.  We’re going to live in John’s office, which is above the garage.  It also serves as a guest suite – it has a daybed and a bathroom of course.  So we’ll be living up there for as long as it takes them to finish up in here. (Hopefully a week to ten days.)

Plus it’s my daughter’s birthday tomorrow and we are going to VA for a day trip to celebrate!  It’s also my cousin Irene’s birthday – so it’s a double celebration! Busy, busy, busy.

Little Choptank 2015 J October 262

The plans call for them to break through in the mudroom and add double doors into the back hallway of the “addition” a/k/a the house.  This was the requirement to make it an addition….only the one entry.  Then, they are tearing down the wall of the bathroom in the Crab Shack where the sink is now and re-configuring the bathroom (except for the shower) to make it bigger.

Little Choptank 2013  H August 2 to Sept 4 500

We’re also adding a tub – which actually was the cause of much conversation as to what tub we would get.  We were going to get one of those beautiful stand alone tubs, that was our decision for a long time.

Capture.2

Then we realized that a lot of the guests who would actually use the tub would not find it that convenient to get into and out of.  So then we went to a drop in tub.  They are also beautiful and we’d have the tile surround and have Fernando (lead builder) make wainscoting to go in the front.

Here was my vision – not the tile all the way up to the ceiling, but maybe a third of the way.  The shower and tub placement are like they will be in the Crab Shack:

 

Capture.4

 

So we went to Seaford, Delaware where the plumbing showroom was (had great Pizza there at Sal’s by the way) and gave Karen from Elegant Designs Showroom our plans to make sure everything would fit.  Well, surprise, surprise and not in a good way….we don’t have room for a drop in tub!!  So if we want to completely change the floor plans (a definite NO) then we had one choice – a slide in tub.  A plain old tub.  It’s a little fuzzy but here is a picture of the new configuration of the bathroom and closet – where our kitchen is now:

Capture

I was a little disappointed – a “little” in this case meaning “very.”  There’s no room for a tile surround or the wainscoting, although we’ll still have tile around the three sides of it.  But let me tell you, by this point in the project, even though it’s been a very good experience and we’re still happy with the workers and the work, we’re a little tired of it all.  So, we bought the tub and moved on.

The rest of the project is moving along – although slowly it seems.  Everything takes longer than you think.  Everybody says it on a building project as large as this, and it’s so true.  When the actual building started – in March – John thought they’d be done by his birthday – early August.  There’s a reason why we say he could be the president of the optimist club.  I thought they’d be done by my birthday – early October.  But now, we’ll be “thankful” if we get in the house by Thanksgiving!  We’re going to spend it at Chrissy’s in Virginia anyway.

So, next time we’ll be back to the progress as it moved along in July – putting on the metal roof.  Meanwhile, enjoy our sunset.

Little Choptank 2016 G July 089

 

 

What are your thoughts?