The Building Begins

September
7
2016

 

Delivering the Wood

Delivering the Wood

You can imagine that this was an exciting day for us.  Our house (now it’s actually called an “addition” – more on that later) was about to start.  After so many years and so many plans, and changes, and money… here it is….the day!  This guy – we named him Mr. Happy – never smiled.  We figured he hated his job…but we were ecstatic!

Three days later our builders arrived.

The Beginning

The Beginning

Little Choptank 2016 D April 127

Little Choptank 2016 D April 130

Every day there was some progress – all that took about seven days, not counting the weekend.

 

More wood deliveries

More wood deliveries

 

The plywood starts

The plywood starts

 

Meanwhile, John and I decided we wanted to build one of those mileage directional signs.  We had pallets around – some of them pretty beat up, but we were able to salvage a lot of pieces.  And using Pinterest as inspiration, he cut some into shapes, others just with a point, and I painted them and looked up mileage.

Little Choptank 2016 D April 090

He cemented the post down by our little beach area, I think it came out pretty good!

When the plywood was done, the next step was the walls!  I know, we’re getting a little nutty here, but this was thrilling!

Little Choptank 2016 E May 043

Little Choptank 2016 E May 046

With the framing going up, it really started looking like a house.

View from the water

View from the water

 

There’s the Crab Shack, cute, little Katrina Cottage.  If you’ve followed along you already know the cost of building the stand-alone house in the middle of the property wound up being too expensive. (You can read about that here) And if we wanted to do a stand-alone where this “addition” is now, we actually wouldn’t have been able to!  Rules have changed, and we would have had to build farther back from the water. There were also many more rules and regulations that would have to be met…such as sprinklers in every room.  Now sprinklers are a good idea, don’t get me wrong.  But we feel they should be the choice of the homeowner.  They are also very expensive, AND…down here, we all have wells for our water.  The well would not be able to keep up with the demand if there should be a fire!  So, some people (we’ve been told) have added huge tanks to hold water!  At great expense!  Crazy.  So, we went down to town hall to find out if it would be possible to “add-on” to the Crab Shack, and even though we all love it, we are changing it a bit inside and adding our “house” to it!  More on this in a future post.

So as the framing is getting worked on, we get this delivery….roof trusses!  The truck was gigantic, the driver was extremely adept at maneuvering, and then he just lifted the back of the cab and let them fall off!  I was shocked!  But don’t worry, they were fine.

Roof trusses

Roof trusses

 

He just drops them!

He just drops them!

 

Next post, we’ll see the trusses getting installed, and some more awesome drone pictures!  Come back and see!  Meanwhile, enjoy the white heron and a beautiful sunset.

Little Choptank 2016 G July 012.jpg cropped

Little Choptank 2016 G July 089

 

 

 

It All Starts with a Good Foundation

 

 

August
31
2016

 

The project finally begins!

The project finally begins!

Yeah, I know.  It’s been awhile.  Don’t remind me.  First nothing was going on.  Then everything.  I will try to get back on track here and update you all with the progress.  And progress there has been!

The first thing that goes on when building a house, of course, is the foundation.  I never knew what went into it, cement I figured, but I never gave it too much thought.  But seeing the progress day by day, it truly was amazing just how many man hours and how much material went into what is underneath my house, stuff you are never going to see.

First they marked the area with red paint.  Thank goodness it didn’t rain before they came back to start digging!

Strings and red paint

Strings and red paint

And it begins!

And it begins!

They start prepping the site

They start prepping the site

 

 

Believe it or not, it's very precise

Believe it or not, it’s very precise

During the few days it took to do all these trenches, it would rain. It was very slow going for a while because they would have to wait for it to dry out before any more work could be done.

Then, they accidentally cut our water line and a temporary fix was done – a hose.  Which we are still using until it’s time to start working on the well.  Believe it or not, the pressure is better now!

Hose being used for water to the Crab Shack and the electric  line is covered up for protection

Hose being used for water to the Crab Shack and the electric line is covered up for protection

 

Next rebar goes in for support.

Little Choptank 2016 C March 188

Little Choptank 2016 C March 189

Next comes the cement….

IMG_1187

What couldn’t be poured directly from the truck had to be moved with a large metal bucket.  It was very labor intensive!

IMG_1203

After all the cement was poured, again the rain delayed the process.  The workers had to clean off the cement a few days!

Little Choptank 2016 C March 260

So, it mostly dried out, and now the dirt has to be moved and the site cleaned up.

IMG_1261Little Choptank 2016 C March 271

Okay, now after the site it cleaned up, there are red lines drawn on the cement, and in come the cement blocks!

Little Choptank 2016 C March 319

Little Choptank 2016 C March 326

Little Choptank 2016 C March 334Little Choptank 2016 C March 355

They build them and level them, you would think it’s easy, but with laying the mortar just so, and leveling them off each time, it’s a tremendously labor intensive process.

Little Choptank 2016 C March 378

IMG_1351

Next they “parged” the outside area of cinder blocks.  It’s a cement plaster that makes a smooth surface.

Little Choptank 2016 C March 368

Next came piles of dirt and they rolled on a black tar-like substance….waterproofing.

Little Choptank 2016 C March 387

Little Choptank 2016 C March 390

Little Choptank 2016 C March 399

More metal is inserted to make the blocks even stronger…..

Little Choptank 2016 C March 391

And here comes the inspector….

Little Choptank 2016 C March 396

So, all was well and good, and the work continued.  So far this took about a week to ten days.  The dirt is spread…..

Little Choptank 2016 C March 417

Little Choptank 2016 C March 419

Here is an awesome picture of the entire foundation with the dirt all finished.  John took it with our drone.  You can see the area between the Crab Shack (Katrina Cottage) and the new addition. We wanted to join the two buildings and hopefully this area, which will have a bathroom and the laundry room, will look like it belongs.

The area (grey-ish dirt) to the right of the pool was where the old house was.  We bought the property knowing it had to be knocked down, although it was more expensive and a much bigger production that we thought.

Little Choptank 2016 C March 451

So at this point, we thought the foundation was finished.  But it wasn’t.  Now it needed rocks!

Little Choptank 2016 C March 487

Little Choptank 2016 C March 490

You see the concrete blocks sitting around in piles…. now it’s their turn to get cemented….

Little Choptank 2016 C March 556

And so, finally, finally the foundation is complete.  It took a month from the time the foundation started to the day we got a wood delivery – so the actual building could begin!

Little Choptank 2016 C March 557

Come back next week to see the progress.  Enjoy the rainbow ( a good omen in my opinion) and the sunset.

Little Choptank 2016 E May 024

Little Choptank 2016 C March 292